Home › EICR
Certificate renewals

Electrical inspections (EICR), at least every 5 years

In England, a private landlord must have the fixed electrical installation in a rented home inspected and tested by a qualified person at least every five years, obtain a report — usually an Electrical Installation Condition Report (EICR) — and give a copy to the tenant.

Last checked against official sources on 26 November 2026 by the editorial team.

The duty comes from the Electrical Safety Standards in the Private Rented Sector (England) Regulations 2020. The official guidance was updated in 2025 when similar duties were extended to social landlords; the private-rented duties described here were already in force. Source: GOV.UK electrical safety guidance, applies to England.

What has to be inspected

The inspection covers the fixed electrical parts of the home: the wiring, socket-outlets, light fittings and the consumer unit (the fuse box).

The work must be done by a qualified person, meaning someone competent to carry out the inspection and testing. You can look for a registered electrician through a competent person scheme.

The report, tenants and the council

The official guidance says you must:

  • have the installation inspected and tested at least every 5 years, or by any earlier next-inspection date on the current report
  • obtain a report (usually an EICR) that gives the results and sets a date for the next inspection and test
  • give a copy to a new tenant before they occupy the property
  • give a copy to an existing tenant within 28 days of the inspection and test
  • give a copy to a prospective tenant within 28 days of a request
  • give a copy to the local council within 7 days of a request
  • keep a copy until the next inspection is due, or until a later report replaces it, and provide it to the person who does the next inspection

If the report says remedial work or further investigation is needed, you must complete that work within 28 days, or any shorter period the report specifies as necessary. Within 28 days of finishing the work you must give the tenant and the local council the report and written confirmation from the qualified person who carried it out. Source: GOV.UK.

A new installation, such as a new-build or a rewire, is usually certified with an Electrical Installation Certificate (EIC) rather than an EICR. England’s landlord register accepts either: an EICR with its next-inspection date, or an EIC with its issue date.

Wales and Scotland

The five-year timetable and the 28-day rules above are the English regulations. Landlords in Wales and Scotland should follow their own national guidance. The landlord register checker on this site is for England only; if you enter a postcode outside England it explains which scheme applies instead.

England’s landlord register

When you register a let property you have 28 days to add the EICR and its next-inspection date, or an EIC and its issue date. If that date is reached, you have another 28 days to update the register entry with the new report.

How long each certificate lasts

The register asks for these records, and each one expires on its own cycle. The guides below set out the official rules, with sources.

How often must a rented home in England have an electrical inspection?

At least every 5 years, and sooner if the report sets an earlier next-inspection date. Source: GOV.UK electrical safety guidance.

What is the difference between an EICR and an EIC?

An EICR (Electrical Installation Condition Report) is the usual report after an inspection of an existing installation. An EIC (Electrical Installation Certificate) is issued for a new installation, such as a new build or a rewire. England’s landlord register accepts either, with different dates.

When must I give the report to the tenant?

To a new tenant, before they occupy the property. To an existing tenant, within 28 days of the inspection and test. A prospective tenant who asks for it must get a copy within 28 days of the request.

What if the report says work is needed?

You must complete any remedial or further investigative work within 28 days, or any shorter period the report specifies as necessary. Within 28 days of finishing that work you must give the tenant, and the local council, the report and written confirmation from the qualified person who did the work.

Does this guide cover Wales and Scotland?

The five-year inspection duty described here is the English one. Wales and Scotland have their own electrical safety rules for rented homes. This site’s landlord register section covers England only.